BEHIND THE SCENES OF OUR INSTALLATIONS AND GENERATOR SYSTEM DESIGN PROJECTS
Our case studies – bringing our projects to life for clients across Kent and the south of England. Learn more about the skills that CSL Power Systems Ltd brings to the table and join our growing number of happy clients today.
OUR TEAMS IN ACTION, WORKING WITH KENT AND THE WIDER UK
CSL Power Systems has completed a wide range of interesting and significant projects across the UK and Europe, setting roots in Honiton and Kent. From new generators to major system overhauls, our team brings more than 20 years' expertise and a professional attitude to every project, and we wanted to share some of those works with you. Explore our various cases studies below or contact us to discuss taking your own plans to fruition.
WATFORD - OCTOBER 2016
The end user, a global data storage facility provider, commissioned a further data hall at an existing data centre in Watford. There was a requirement for further standby power complete with an autonomous fuel system. The generators are located within acoustic enclosures mounted on top of underslung bulk fuel tanks. A new switchboard inside a weatherproof enclosure is situated adjacent to the new generators.
DATA CENTRE IN SLOUGH - DECEMBER 2015
"I am happy to advise that the guys who executed the task were extremely professional and solved a few last-minute challenges with excellent problem solving and determination...I look forward to future business."
An existing, operational data centre with three generator halls in use, 2 generators in each room and one lying fallow was to be enhanced with further power requirements. Each of the existing rooms was to have a third generator incorporated into the existing system and the fallow room was to be equipped with three generators to provide back-up power to a newly commissioned data hall.
WATER TREATMENT WORKS IN HARLOW
"Thanks for arranging one of your engineers to attend site at short notice and assist with the identification of the missing telemetry signals... it made the task much quicker and allowed us to carry out the work within the planned site shutdown period."
Theft of the original equipment necessitated the replacement of a standby generator at a water treatment works in Harlow, Essex.
​
CSL Power Systems were assigned with placing a Cummins C150D5 canopied generator inside an existing acoustic enclosure and encasing it in concrete blocks with reinforced concrete infill.
​
The existing enclosure had been damaged when the original equipment was stolen and the end section had been forcibly removed. Once the new set was inside the enclosure the end section was replaced and secured. The entire acoustic enclosure was then encased within a concrete block structure with rebars and concrete infill along with a concrete ring beam to the top level and steel beams across the roof section affording extra protection against further theft of equipment.
​
The generator was coupled to an existing bulk fuel tank and a new auto transfer switch replaced existing equipment.
​
A full test of existing and new systems was undertaken upon completion.
DATA CENTRE IN MIDDENMEER, HOLLAND
"We were very impressed with what you provided us from design to your installation team who done a great job"
A large data centre was commissioned to be constructed for a world leading IT company. The standby power requirements for this facility consist of 20 Cummins C3500D5e generators and 4 Cummins C2000D5e generators in acoustic enclosures. Each set has an underslung base tank and local fill point local to the bund area below each generator enclosure. Each enclosure has a dedicated section located to one end which houses the generator switchboard.
DATA CENTRE IN CRAWLEY, NOVEMBER 2016 – MAY 2017
"All CSL personnel were professional and courteous throughout the complete installation process."
In 2014 a data centre was built close to Gatwick airport. The original design had all of the MV transformers, standby generators, air handling units and other items of plant situated on the roof of the structure. As a result of this design there were numerous penetrations through the roof fabric which resulted in leaks forming in the roof and subsequently water penetration into the data halls. To rectify the problem a further roof structure has been formed which covers all of the existing equipment to form a weatherproof solution to the initial problem.
CHESSINGTON - NOVEMBER 2014 AND JUNE 2016
(PHASE 1 & 2)
"I would just like to compliment CSL on your professionalism and swift engagement at every stage of the way. I would recommend CSL to any future clients for all generator and data centre works."
​In 2014 Digital Realty took possession of a former distribution centre in Chessington with the intention of adapting the building to use it as a data centre. The project was carried out across two phases with two data halls being completed in phase 1, 2014/15 and the third data hall being completed in phase 2, 2016. The rooms allocated for the installation of the standby generators were of limited spatial allowance and this posed many obstacles as the equipment had to be installed in a strict sequence and as there was no storage space on site during the works the materials and equipment had to be delivered to suit the installation sequence. A crane had to be utilised to offload the generators within the tight constraints of the construction site.
If you’d like to learn more about any of our cases studies, please call 01474 823030 for further details and discuss your individual project.
Unit 1, Pedham Place Farm, London Rd
Farningham, Dartford, Kent, DA4 0JW